Question: Using the data shown in E8-16, calculate the following overhead variances: In e8-16, Production for the month . . . . . . . .
Using the data shown in E8-16, calculate the following overhead variances:
In e8-16,
Production for the month . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9,000 units
Direct labor hours used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18,500 hours
Factory overhead incurred for:
Variable costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$28,500
Fixed costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$52,000
a. Spending variance.
b. Production-volume variance.
c. Efficiency variance.
d. Was the factory overhead under-or over-applied? By what amount?
Step by Step Solution
3.49 Rating (172 Votes )
There are 3 Steps involved in it
a b c d Actual factory overhead 80500 Applied factory overhead 1... View full answer