Question: Variance analysis, materials and labor Pharout Company uses a standard cost system. Job 822 is for the manufacturing of 500 units of the product P521.
Variance analysis, materials and labor Pharout Company uses a standard cost system. Job 822 is for the manufacturing of 500 units of the product P521. The company's standards for one unit of product P521 are as follows:

The job required 2,800 ounces of raw material costing $5,880. An unfavorable labor rate variance of $250 and a favorable labor efficiency variance of $100 also were determined for this job.Required(a) Determine the direct material price variance for job 822 based on the actual quantity of materials used.(b) Determine the direct material quantity variance for job 822 based on the actual quantity of materials used.(c) Determine the actual quantity of direct labor hours used on job 822.(d) Determine the actual labor costs incurred for job822.
PRICE QUANTITY Direct material PRICE $2 per ounce $10 per hour 5 ounces Direct labor 2 hours
Step by Step Solution
3.46 Rating (172 Votes )
There are 3 Steps involved in it
a b Direct material quantity variance AQ SQ SP 2800 5 500 2 600 U c A favorable labor ... View full answer