Question: You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week
At the end of week 3:
What is your SPI?
What is your CPI?
What is your EAC?
Step by Step Solution
3.50 Rating (163 Votes )
There are 3 Steps involved in it
SPI Schedule Performance Index Earned value Planned Value Planned value at the end of three week pla... View full answer