Question: You have run a capacity resource profile on your shop. Products have been routed sequentially through resources A, B, C, and D. The capacity resource
You have run a capacity resource profile on your shop. Products have been routed sequentially through resources A, B, C, and D. The capacity resource profile tells you that resource A is scheduled at 95% of capacity, resource B at 80% of capacity, resource C at 130% of capacity, and resource D at 100% of capacity. Assuming that the data we used to calculate the capacity resource profile was accurate, how would you employ the “drum, buffer rope” thinking?
Step by Step Solution
3.46 Rating (169 Votes )
There are 3 Steps involved in it
The drum or control of the process is at the bottleneck resource C A little buffer ... View full answer