Question: Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project's ETC. Activity A is

Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project's ETC.
Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It is at the end of Week 3 of 5. Activity B is 85% complete at a cost so far of $150,000. It was estimated to cost $80,000 when finished. It is at the end of Week 4 of 5. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 when finished. Assume spending will continue at the same rate.

Step by Step Solution

3.44 Rating (179 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

For Activity A 60 is complete at cost of 50000 Amount requir... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(1852).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!