Your project is progressing well in your estimation. Your team has collected the following data. From these

Question:

Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project's ETC.
Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It is at the end of Week 3 of 5. Activity B is 85% complete at a cost so far of $150,000. It was estimated to cost $80,000 when finished. It is at the end of Week 4 of 5. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 when finished. Assume spending will continue at the same rate.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Business Statistics A Decision Making Approach

ISBN: 9780133021844

9th Edition

Authors: David F. Groebner, Patrick W. Shannon, Phillip C. Fry

Question Posted: