Question: 1. An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The

1. An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest takes .3 minute. The line will operate for 480 minutes per day.
a. What are the maximum and minimum cycle times?
b. How much daily output will be achieved by each of those cycle times?
2. In Problem 5, suppose the line is balanced using 10 workstations and a finished product can be produced every 4.2 minutes.
a. What is the production rate in units per day?
b. What is the assembly line efficiency?

Step by Step Solution

3.42 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 a Minimum cycle time length of longest task which is 2... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

68-B-E-M-E (1957).docx

120 KBs Word File

Students Have Also Explored These Related Economics Questions!