Question: 1. Analyze the case data and current schedule, and answer the following baseline questions. Whats labor utilization for each thirty-minute period given their current staffing
2. What is the cost of abandon and busy signal calls for this typical Monday day? Annually? (State and make assumptions as needed).
3. Develop a better CSR staff schedule (see Excel posted current staff schedule) if needed and decide whether they should hire more CSRs or layoff a few. Will you use part-time employees? If so, explain why and justify.
4. What are your final recommendations? Explain and justify.
Step by Step Solution
3.41 Rating (170 Votes )
There are 3 Steps involved in it
1 See TN Exhibits A B C to answer issues in case question 1 From Exhibit B we see that current CSR utilization ranges for 38 to 160 with high variabilitythis is evidence of a scheduling problem From E... View full answer