Question: 1. Compute the average flow time, lateness, and tardiness for this group of jobs using Mr. Sailboats sequential order of 1 (first), 2, 3, 4,
2. In what order would the jobs be processed using the SPT rule? Compute the average flow time, lateness, and tardiness for this group of jobs.
3. Compare the answers in questions 1 and 2.
4. What are your short-term recommendations for this set of six jobs? Justify and explain
5. What are your long-term recommendations with respect to sequencing jobs at Balloons Aloha? Justify and explain.
Step by Step Solution
3.51 Rating (185 Votes )
There are 3 Steps involved in it
1 2 The order would be 264531 3 SPT minimizes the average time a job spends in the shop either waiti... View full answer