Question: 1. Develop a CPM/PERT network for Moore House Contractors and determine the probability that the contractors can complete a house within 45 days. Does it
2. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. Also indicate which activities the company might shift workers from as the need arises.
Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer into the fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready—sometimes before.
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
a Activity Activity Activity Duration Variance ES LS EF LF Slack a 4167 25 0 0000 4167 4167 C r i t i c a l b 3167 25 4167 4167 7333 7333 C r i t i c a l c 3833 25 7333 7833 11167 11667 500 d 2167 25 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
184_606c794a89a9f_143870.xlsx
300 KBs Excel File
184-B-M-L-O-M (469).docx
120 KBs Word File