Question: 1. Develop the MRP for all of the components. 2. During week 1 of the plan the bracket supplier notifies CFC that the order for

1. Develop the MRP for all of the components.

2. During week 1 of the plan the bracket supplier notifies CFC that the order for 600 units will not arrive as planned. Instead, 300 will arrive this week and 300 will arrive next week, instead of all 600 arriving at the same time. Will this affect production, and if so, to what extent?

3. Now that the plan has been developed, is it feasible considering the capacity of the cutting department? What recommendations do you have?

4. If you could change the lead times or lot sizing policies used for any of the components, what changes would you make? Why?

Step by Step Solution

3.53 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Part Name Bookshelf 4X301 Leadtime 0 Order Quantity Lot for lot Week Week Week Week Week Week Week Week 1 2 3 4 5 6 7 8 Gross Requirements 70 70 80 90 60 80 80 70 Scheduled Receipts On Hand Inventor... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

434-B-M-L-S-C-M (2519).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!