Question: 1. Draw the appropriate network diagram. 2. Find the Critical Path and the project completion time. 3. Find the Probability that the project will take
1. Draw the appropriate network diagram.
2. Find the Critical Path and the project completion time.
3. Find the Probability that the project will take more than 50 days to complete. Please use excel and show work, including formulas?
.png)
Time, in Days St. Dev Predecessor Job 1.17 a 3 1.5 3 1.5 b.c d. 4 1 b,c 1.5 1.17 0.67 df h 2.
Step by Step Solution
3.31 Rating (172 Votes )
There are 3 Steps involved in it
Path Duration In Days a b d g h 7 3 4 8 6 28 days a b c d g h 7 3 9 4 8 6 ... View full answer