Question: The following activity time estimates, in days, are for a construction project planned by Curtis Construction Company: Required: (1) Compute the expected completion time for

The following activity time estimates, in days, are for a construction project planned by Curtis Construction Company:

The following activity time estimates, in days, are for a

Required:
(1) Compute the expected completion time for activity 3-4.
(2) Construct a PERT network of the activities and events necessary to complete the construction project.
(3) Determine the estimate time required to complete each path through the PERT network, and identify the critical path.
(4) What is the slack time for event 2?

Activity tmost optimistic time mmost likely time 0-1 most pessimistic time estimated completion time 2-6 3-4 3-5 4-6 4-7 5-7 6-7 6 6 6 2 6

Step by Step Solution

3.38 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 t e t o 4t m t p 6 1 4 2 9 6 3 days 2 3 Path Time Re... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

906-B-M-A-P-C (2765).docx

120 KBs Word File

Students Have Also Explored These Related Managerial Accounting Questions!