Question: 1. For E5-15, prepare a cost of production summary for the month for Finishing. In E5-15, Hanover Inc. has two production departments. Finishing had 2,000
1. For E5-15, prepare a cost of production summary for the month for Finishing.
In E5-15, Hanover Inc. has two production departments. Finishing had 2,000 units in process at the beginning of the period, three-fifths complete. During the period, 14,000 units were received from Assembly, 13,000 units were transferred to the finished goods storeroom, and 3,000 units were in process at the end of the period, two-thirds complete. The cost of the beginning work in process was:
Cost in Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $12,000
Cost in Finishing:
Materials . . . . . . . . . . . . . . . . . . . . . . . ...... 600
Labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... 1,500
Factory overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .900
The costs during the month were:
Cost of goods received from Assembly . . . . . . . . . . . . . . . $84,000
Cost in Finishing:
Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... 4,800
Labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15,000
Factory overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9,600
2. Prepare a journal entry to transfer the completed units from Finishing to the finished goods storeroom.
Step by Step Solution
3.43 Rating (162 Votes )
There are 3 Steps involved in it
1 2 Finished Goods106080 Work in ProcessFinishing 106080 Cost of Production Summary Finishing Dep... View full answer