Question: 1. Using the data in E, prepare a cost of production summary for the month ended January 31, 2016. In E, Chavez Concrete Inc. has
In E, Chavez Concrete Inc. has two production departments. Blending had 1,000 units in process at the beginning of the period, two-fifths complete. During the period 7,800 units were received from Mixing, 8,200 units were transferred to the finished goods store- room, and 600 units were in process at the end of the period, 1/3 complete. The cost of the beginning work in process was:
Cost in Mixing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $10,000
Cost in Blending:
Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200
Labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 500
Factory overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 300
The costs during the month were:
Cost of goods received from Mixing . . . . . . . . . . . . . . $78,000
Cost in Blending:
Materials. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3,328
Labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10,000
Factory overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6,672
2. Prepare a journal entry to transfer the cost of the completed units from Blending to the finished goods storeroom.
Step by Step Solution
3.48 Rating (164 Votes )
There are 3 Steps involved in it
1 Chavez Concrete Inc Cost of Production Summary Blending Department January 31 2016 Cost of work in ... View full answer