a. Assuming that the two plans have the same risk as the firm, use the following capital

Question:

a. Assuming that the two plans have the same risk as the firm, use the following capital budgeting techniques and the firm’s cost of capital to evaluate their acceptability and relative ranking.

(1) Net present value (NPV).

(2) Internal rate of return (IRR).

b. Recognizing the differences in plan risk, use the NPV method, the risk-adjusted discount rates (RADRs), and the data given earlier to evaluate the acceptability and relative ranking of the two plans.

c. Compare and contrast your finding in parts a and b. Which plan would you recommend? Did explicit recognition of the risk differences of the plans affect this recommendation?

d. Use the real-options data given above for each plan to find the strategic NPV, NPVstrategic, for each plan.

e. Compare and contrast your findings in part d with those in part b. Did explicit recognition of the real options in each plan affect your recommendation?

f. Would your recommendations in parts a, b, and d change if the firm were operating under capital rationing? Explain.


Cherone Equipment, a manufacturer of electronic fitness equipment, wishes to evaluate two alternative plans for increasing its production capacity to meet the rapidly growing demand for its key product—the Cardiocycle. After months of investigation and analysis, the firm has pruned the list of alternatives down to the following two plans, either of which would allow it to meet its forecast product demand.

Plan X

Use current proven technology to expand the existing plant and semi-automated production line. This plan is viewed as only slightly more risky than the firm’s current average level of risk.

Plan Y

Install new, just-developed automatic production equipment in the existing plant to replace the current semi-automated production line. Because this plan eliminates the need to expand the plant, it is less expensive than Plan X, but it is believed to be far more risky because of the unproven nature of the technology.

Cherone, which routinely uses NPV to evaluate capital budgeting projects, has a cost of capital of 12%. Currently the risk-free rate of interest, RF, is 9%. The firm has decided to evaluate the two plans over a 5-year time period, at the end of which each plan would be liquidated. The relevant cash flows associated with each plan arc summarized in the following table.


a. Assuming that the two plans have the same risk


The firm has determined the risk-adjusted discount rate (RADR) applicable to each plan as shown in the following table.
Plan Risk adjusted Discount rate (RADR)
X..........13%
Y ...........15%

Further analysis of the two plans has disclosed that each has a real option embedded within its cash flows.
Plan X Real Option—At the end of 3 years the firm could abandon this plan and install the automatic equipment, which by then would have a proven track record. This abandonment option is expected to add $100,000 of NPV and has a 25% chance of being exercised.
Plan Y Real Option—Because plan Y does not require current expansion of the plant, it creates an improved opportunity for future plant expansion. This option allows the firm to grow its business into related areas more easily if business and economic conditions continue to improve. This growth option is estimated to be worth $500,000 of NPV and has a 20% chance of beingexercised.

Net Present Value
What is NPV? The net present value is an important tool for capital budgeting decision to assess that an investment in a project is worthwhile or not? The net present value of a project is calculated before taking up the investment decision at...
Internal Rate of Return
Internal Rate of Return of IRR is a capital budgeting tool that is used to assess the viability of an investment opportunity. IRR is the true rate of return that a project is capable of generating. It is a metric that tells you about the investment...
Capital Budgeting
Capital budgeting is a practice or method of analyzing investment decisions in capital expenditure, which is incurred at a point of time but benefits are yielded in future usually after one year or more, and incurred to obtain or improve the...
Cost Of Capital
Cost of capital refers to the opportunity cost of making a specific investment . Cost of capital (COC) is the rate of return that a firm must earn on its project investments to maintain its market value and attract funds. COC is the required rate of...
Discount Rate
Depending upon the context, the discount rate has two different definitions and usages. First, the discount rate refers to the interest rate charged to the commercial banks and other financial institutions for the loans they take from the Federal...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Principles of managerial finance

ISBN: 978-0132479547

12th edition

Authors: Lawrence J Gitman, Chad J Zutter

Question Posted: