Question: A certain customer has placed an order for 50,000 gizmos that need to be produced during the next five days. If the factory operates a
A certain customer has placed an order for 50,000 gizmos that need to be produced during the next five days. If the factory operates a single eight-hour shift, what is the takt time for this order, allowing 10% nonproductive time for breaks and machine downtime?
Step by Step Solution
3.44 Rating (157 Votes )
There are 3 Steps involved in it
Number of shifts 1 shiftday ... View full answer