The demand for a certain customer is 50,000 gizmos to be produced during the next five days.

Question:

The demand for a certain customer is 50,000 gizmos to be produced during the next five days. If the factory operates a single eight-hour shift, what is the takt time for this order, allowing 10% nonproductive time for breaks and machine downtime?