Question: A company has just received a contract for 700 units of a certain product. The pricing department has predicted that the first unit should require
A company has just received a contract for 700 units of a certain product. The pricing department has predicted that the first unit should require 2,250 hours. The pricing department believes that a 75 percent learning curve is justified. If the actual learning curve is 77 percent, how much money has the company lost? Assume that a fully burdened hour is $65. What percentage error in total hours results from a 2 percent increase in learning curve percentage?
Step by Step Solution
3.32 Rating (167 Votes )
There are 3 Steps involved in it
Using the computer program for a 75 learning curve the tot... View full answer