A construction project has the following network and activity times: a. Make a forward pass and a
Question:
a. Make a forward pass and a backward pass on the activity times.
b. Find the slack for each activity.
c. Prepare a Gantt chart for this project.
d. Activity D will be delayed by one day. What effect will this have on the project?