Question: A designer estimates that she can (a) Increase the average time between failures of a part by 5 percent at a cost of $ 450,
(a) Increase the average time between failures of a part by 5 percent at a cost of $ 450, or
(b) Reduce the average repair time by 10 percent at a cost of $ 200. Which option would be more cost-effective? Currently, the average time between failures is 100 hours and the average repair time is 4 hours.
Step by Step Solution
3.52 Rating (169 Votes )
There are 3 Steps involved in it
a Increase in MTBF cost 450 05100 5 hrs New MTBF 100 5 105 hrs b Reduc... View full answer