Question: A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations
A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table:
.png)
.png)
Construct the network for this project, identify the critical path, and determine the project durationtime.
Activity Ativity Duration Predecessor Activity Activity Description (weeks) Excavate b Erect building Install generator Install tank 4 d 4. f Connect generator and tank to building b, c, d Paint finish Check out facility
Step by Step Solution
★★★★★
3.41 Rating (167 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Critical path a b h 15 weeks a ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
300-B-F-F-M (3515).docx
120 KBs Word File