Question: Given the following network and activity time estimates, determine the expected time and variance for each activity and indicate the criticalpath: 5 7,9,20 9 10,15
.png)
5 7,9,20 9 10,15 4.121 4 10,1 Start Finish 27.16 2,9,14 7 3,6,9 5,9.16 10 4,121 3 4,8.11
Step by Step Solution
3.42 Rating (171 Votes )
There are 3 Steps involved in it
Activity 1 2 3 4 5 6 7 8 9 10 11 a 16 2 4 3 7 4 3 5 3 ... View full answer