Question: a. Given the following forecast and steady regular output of 550 every month, what total cost would result if overtime is limited to a maximum
a. Given the following forecast and steady regular output of 550 every month, what total cost would result if overtime is limited to a maximum of 40 units a month, and subcontracting is limited to a maximum of 10 units a month? Unit costs are:
Regular output $ 20
Overtime $ 30
Subcontract $ 25
Average Inventory $ 10
Backlog $ 18
b. Suppose now that backlogs are not allowed. Modify your plan from part a to accommodate that new condition as economically as possible. The limits on overtime and subcontracting remain the same.
Month Forecast 540 540 570 590 600 580
Step by Step Solution
3.45 Rating (171 Votes )
There are 3 Steps involved in it
Given Use regular output of 550 units per month Use a maximum of 40 units of overtime per month and a maximum of 10 units of subcontracting per month ... View full answer