Question: A large precast concrete panel for a warehouse is being raised to a vertical position using two sets of cables at two lift lines as
Find the required cross-sectional area AC of the cable if its breaking stress is 91 ksi and a factor of safety of 4 with respect to failure is desired.
.png)
2 2
Step by Step Solution
3.42 Rating (165 Votes )
There are 3 Steps involved in it
GEOMETRY Using Law of cosines L 2 6425 ft ... View full answer