Question: A large precast concrete panel for a warehouse is being raised to a vertical position using two sets of cables at two lift lines as

A large precast concrete panel for a warehouse is being raised to a vertical position using two sets of cables at two lift lines as shown in the figure part (a). Cable 1 has length L1 = 22 ft and distances along the panel (see figure part (b)) are a = L1/2 and b = L1/4. The cables are attached at lift points B and D and the panel is rotated about its base at A. However, as a worst case, assume that the panel is momentarily lifted off the ground and its total weight must be supported by the cables. Assuming the cable lift forces F at each lift line are about equal, use the simplified model of one half of the panel in figure part (b) to perform your analysis for the lift position shown. The total weight of the panel is W = 85 kips. The orientation of the panel is defined by the following angles: γ = 20° and θ = 10°.
Find the required cross-sectional area AC of the cable if its breaking stress is 91 ksi and a factor of safety of 4 with respect to failure is desired.
A large precast concrete panel for a warehouse is being

2 2

Step by Step Solution

3.42 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

GEOMETRY Using Law of cosines L 2 6425 ft ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

836-P-M-S (91).docx

120 KBs Word File

Students Have Also Explored These Related Mechanics Questions!