Question: A major utility company has a planning group that prepares budgets (with the help of functional groups) and selects the projects to be completed within
A major utility company has a planning group that prepares budgets (with the help of functional groups) and selects the projects to be completed within a given time period. You are assigned as a project manager on one of the projects and find out that it should have been started “last month” in order to meet the completion date. What can you, the project manager, do about this? Should you delay the start of the project to replan the work?
Step by Step Solution
3.42 Rating (152 Votes )
There are 3 Steps involved in it
You must not delay the start date to do the replanning or else ... View full answer