Question: A new engineer is evaluating whether to use a higher voltage transmission line. It will cost $250,000 more initially, but it will reduce transmission losses.
(a) What is the present worth (of cost and benefits) for each estimated value?
(b) Use the range of estimates to compute the mean annual savings, and then determine the present worth.
(c) Would you recommend the higher voltage line? Give both economic and noneconomic reasons.