Question: 1 . A new engineer is evaluating whether to use a higher - voltage transmission line. It will cost ( $ 2 5
A new engineer is evaluating whether to use a highervoltage transmission line. It will cost $ more initially, but it will reduce transmission losses. The optimistic with probability most likely with probability and pessimistic projections for annual savings are $ $ and $ respectively. The interest rate is and the transmission line should have a life of years.
a Find the probability of the pessimistic projection. points
b What is the present worth PW for each estimated value? points
c What is the expected value for the present worth? points
d What is the risk of this present worth use variance equation, then take the square root points