Question: A paper mill has decided to implement a control chart to monitor the weight of the paper that it is producing. DS 16.6.1 contains the
(a) Does it look as though the paper producing process was in control when this data set was collected?
(b) What control charts would you suggest are used to monitor future runs of paper production?
(c) What conclusion would you draw if in the future a sample x1 = 76.01, x2 = 73.42, and x3 = 72.61 is obtained?
(d) What if x1 = 77.82, x2 = 79.04, and x3 = 75.83?
Step by Step Solution
3.38 Rating (154 Votes )
There are 3 Steps involved in it
a Sample 3 appears to have been out of control b If sample 3 is removed then the fol... View full answer