Question: A plant engineering group needs to set up an assembly line to produce a new product. The following table describes the relationships between the activities
.png)
If using Crystal Ball, assume that the duration of each activity follows a BetaPert distribution, with the three time estimates shown for that activity. Otherwise, assume that each activity time is normally distributed with expected time and standard deviation computed as shown in equations 7-6 and 7-8, respectively, on page 283. Round off all activity times to two decimal places.
(a) Use simulation to determine the probability that the project will finish in 37 days or less.
(b) Use simulation to determine the probability that the project will take more than 32 days.
DAYS IMMEDIATE ACTIVITY a m bPREDECESSORS 8 10 B, C 17 9 12 F. G E, F, H
Step by Step Solution
3.27 Rating (171 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
718-M-S-L-P (1289).xlsx
300 KBs Excel File