A plant has four operators to be assigned to four machines. The time (minutes) required by each

Question:

A plant has four operators to be assigned to four machines. The time (minutes) required by each worker to produce a product on each machine is shown in the following table. Determine the optimal assignment and compute total time in minutes using the Hungarian method.
Machine (min.) Operator 10 12 10 3 12 14 13 11 15 11