Question: A process is designed to produce 2000 units per hour. The process has a scrap rate of 2% and an 8% inherent inefficiency. Assuming that

A process is designed to produce 2000 units per hour. The process has a scrap rate of 2% and an 8% inherent inefficiency. Assuming that the actual output of the process is 1750 units per hour, what is the process design capacity, available capacity, actual capacity, capacity utilization, efficiency, and output gap for this process?

Step by Step Solution

3.51 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Design capacity 2000 units Available capacity 2000 x ... View full answer