A project has four activities (A, B, C, and D) that must be performed sequentially. The probability

Question:

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:


A project has four activities (A, B, C, and D)


a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
b. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks.
c. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks orless.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Methods for Business

ISBN: 978-0324651751

11th Edition

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey cam

Question Posted: