Question: A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
.png)
a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
b. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks.
c. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks orless.
555 0 55 25 12 0 b 0000 000 00000 00 y el 5678 357 02468 80
Step by Step Solution
3.26 Rating (167 Votes )
There are 3 Steps involved in it
a Base case using most likely completion times A 6 B ... View full answer