Question: A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date,

A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?