Question: A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure P1227.

A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure P12–27. However, the project manager has some information available, specifically that each activity, labeled A–G, has a different duration between one and seven weeks. Also, the slack time for each of the activities is known as shown in Figure P12–27 in ascending order.

Duration (weeks): 1, 2, 3, 4, 5, 6, 7

Slack time (weeks): 0, 0, 0, 2, 4, 4, 7


A project manager discovers that his team has neglected to


Using the clues provided below, determine the duration of each activity as well as the early start, early finish, latest start and latest finish times for each activity.
Clues
1. Activity E is on the critical path.
2. The early start (ES) time for activity F is five weeks.
3. The duration of activity B is seven weeks.
4. Activity D has four weeks of slack, but activity F has a greatest amount of slack.
5. The early finish (EF) time for activity G is seventeen weeks.
6. The latest finish (LF) time for activity E is thirteenweeks.

Activity Duration

Step by Step Solution

3.49 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity Duration ES EF LS LF ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

93-B-M-L-P-M (845).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!