Question: For the network shown in Figure with all times indicating weeks, answer the following questions: a. What is the impact on the end date of
For the network shown in Figure with all times indicating weeks, answer the following questions:
a. What is the impact on the end date of the project if activity I slips by three weeks?
b. By how many weeks can activity D slip before the end date gets extended?
c. If activity A slips by one week, how will the slack in activity G be impacted?
d. If activity H can somehow be compressed from seven weeks to two weeks, perhaps by adding a significant number of resources, what will be the impact, if any, on the end date of theproject?
.png)
START- FINISH
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
a No impact b Anything greater than one week c One week of slack wi... View full answer