A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000,

Question:

A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.