Question: A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
000 Day AC PV EV 70 78 84 81 CV 3 Favorable CPI 104 SV 3 Unfavo... View full answer