A small metal-parts shop contains three machinesa drill press, a lathe, and a grinderand has three operators,
Question:
![A small metal-parts shop contains three machinesa drill press,](https://dsd5zvtm8ll6.cloudfront.net/si.question.images/image/images5/184-B-M-L-S-C-M(598).png)
The shop manager wants to assign one operator to each machine so that the total operating time for all three operators is minimized. Formulate and solve a linear programming model for thisproblem.