Question: A small project consists of three activities: A, B, and C. To start activity C, both activities A and B need to be complete. Activity
A small project consists of three activities: A, B, and C. To start activity C, both activities A and B need to be complete. Activity A takes 3 days with a probability of 50 percent and 5 days with a probability of 50 percent, and so does Activity B. Activity C takes 1 day. What is the expected completion time of the project?
Step by Step Solution
3.40 Rating (163 Votes )
There are 3 Steps involved in it
It takes an expected 55 days That this is longer than one would expect based on the average co... View full answer