Question: A software company is moving its helpdesk operations center from Newark, New Jersey, to Plano, Texas. Some of its employees will be moved to Plano,
A software company is moving its helpdesk operations center from Newark, New Jersey, to Plano, Texas. Some of its employees will be moved to Plano, and others will be terminated and replaced by new workers in Texas. The activities that must be carried out to implement the move are summarized in the following table.
.png)
a. Draw the CPM network for this problem.
b. Create a spreadsheet to calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities.
c. What is the least amount of time required to complete the project?
Activity Description Predecessors Weeks Revise organizational structure Select new office location Determine personnel requirements Design new call center Renovate office space Select employees to move Hire new employees Set up new administrative systems Move office equipment and records Train new employees IS D B, C G E,G, H,I
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
a b c 23 weeks Activity A B D E F G H I J Helpdesk Move Descrip... View full answer