Question: A software development project consists of six activities. The activities and their predecessor relationships are given in the following table. The worksheet Problem 20 in
A software development project consists of six activities. The activities and their predecessor relationships are given in the following table. The worksheet Problem 20 in the Excel file Chapter 10 Problem Data provides a sample of times in weeks for activities A, B, E, and F from 40 past projects.
Activity | Activity Times | Predecessors | |
A | Requirement Analysis | See Excel File | None |
B | Programming | See Excel file | A |
C | Hardware | Constant 3 weeks | A |
D | User Trainnig | Constant 12 weeks | A |
E | Implementation | See Excel file | B, C |
F | Testing | See Excel file | E |
Assume that activity start time is zero if there are no predecessor activities. Fit distributions to the sample data and use Crystal Ball to find the mean project completion time, minimum and maximum project completion times, skewness of the completion time distribution, and probability of completing the project in 14, 15, 16, or 17 weeks.
Step by Step Solution
3.29 Rating (167 Votes )
There are 3 Steps involved in it
The software development model is given below Software Development Project Requirements Analysis Pro... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
749-M-S-S-D (3274).docx
120 KBs Word File