A subcontractor is responsible for outfitting six satellites that will be used for solar research. Four of the six have been completed in a total of 600 hours. If the crew has a 75 percent learning curve, how long should it take them to finish the last two units?

Step by Step Solution

3.36 Rating (177 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Given Four units have been completed in a total of 600 hours Learnin... View full answer