Question: A system has five workstations (A, B, C, D, E) connected in sequence, with process times 5, 10, 4, 9, and 8 seconds per unit
A system has five workstations (A, B, C, D, E) connected in sequence, with process times 5, 10, 4, 9, and 8 seconds per unit each, respectively. Each work station contains a single machine. B. Assume the process runs 24 hours a day, 7 days per week. What is the capacity process per week?
A. 151200
B. 50420
C. 60480
D. 16200
Step by Step Solution
3.34 Rating (157 Votes )
There are 3 Steps involved in it
C 60480 Workstation D has now become the bottleneck as A is delivering 1 unit per 5 minu... View full answer