Question: An assembly line currently has five workstations and the time required for each is shown in the figure below. a. What is the current cycle
.png)
a. What is the current cycle time?
b. What is the efficiency of the process?
c. Customer demand is 80 units per hour. What is the hourly production rate of the current process?
d. What does the cycle time need to be to be able to meet demand (what is the take time)?
e. What changes to the process are needed?
1 50 sec 42 sec. 38 sec 32 sec 45 sec
Step by Step Solution
3.48 Rating (164 Votes )
There are 3 Steps involved in it
a The cycle time is 50 seconds The cycle time is determined by the bottlen... View full answer