Question: A work cell at Chris Ellis Commercial Laundry has a workstation with two machines, and each unit produced at the station needs to be processed

A work cell at Chris Ellis Commercial Laundry has a workstation with two machines, and each unit produced at the station needs to be processed by both of the machines. (The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4 units per hour. What is the process time of the work cell in minutes per unit?

Step by Step Solution

3.45 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ns Thrughut time 1 unit 60 min4 unit... View full answer