Question: After using your forecasting model for six months, you decide to test it using MAD and a tracking signal. Here are the forecast and actual
.png)
a. Find the tracking signal.
b. Decide whether your forecasting routine isacceptable.
PERIOD FORECAST ACTUAL May June July August September 450 500 550 600 650 700 500 550 400 500 675 600 October
Step by Step Solution
3.46 Rating (166 Votes )
There are 3 Steps involved in it
a Month Forecast Actual Deviation RSFE Absolute deviation Sum of ab... View full answer