Question: Always Rain Irrigation, Inc., would like to determine capacity requirements for the next four years. Currently two production lines are in place for making bronze
.png)
Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require two operators and can produce up to 12,000 sprinklers. The plastic injection molding machine needed for the plastic sprinklers re-quires four operators and can produce up to 200,000 sprinklers. Three bronze machines and only one injection molding machine are available. What are the capacity requirements for the next four years? (Assume that there is nolearning.)
YEARLY DEMAND 1 (IN o00s) 2 (IN ooos) IN 000S 3 (IN o00s) IN 00os) Plastic 90 Plastic 180 Plastic 360 Bronze 90 Bronze 180 Bronze 360 32 56 16 50 10 4 6 12
Step by Step Solution
3.56 Rating (170 Votes )
There are 3 Steps involved in it
Plastic Year 1 Year 2 Year 3 Year 4 Demand for plastic sprinklers 97 115 136 1... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
287-B-M-L-S-C-M (1332).docx
120 KBs Word File