Question: An assembly line must be designed to produce 50 packages per hour. The following data in Table 10-17 give the necessary information. (a) Draw a

An assembly line must be designed to produce 50 packages per hour. The following data in Table 10-17 give the necessary information.


An assembly line must be designed to produce 50 packages


(a) Draw a precedence diagram.
(b) Compute the cycle time (in seconds) to achieve the desired output rate.
(c) What is the theoretical minimum number of stations?
(d) Which work element should be assigned to which workstation?
(e) What are the resulting efficiency and balance delaypercentages?

Table 10-17 Task Information for Problem 13 Task Immediate Predecessor Task Time (sec) None 60 35 45 10 50 C, D, E

Step by Step Solution

3.36 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b C 3600 secondshour50 unitshour 72 secondsunit c TM 22... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

194-B-M-L-O-M (2736).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!