Question: An assembly line requires two components: gadjits and widjits. Gadjits are produced by center 1 and widjits by center 2. Each Unit of the end
.png)
The container for gad jits holds 80 units. The policy variable for center us set at 0.09. The average waiting time for a container of gadjits is 009 day. and 0.06 day is needed to produce a container The container for widjits holds 50 units, and the policy variable for center 2 Is 0.08. The average waiting time per container of widgits is 0.14 day, and the time required to process a container is 0.20 day.
a. How many containers are needed for gadjits?
b. How many containers are needed forwidjits?