An emergency situation has occurred in the milling department, because the ship carrying a certain quantity of
Question:
(a) If the production week consists of 10 shifts at 8.0 hr per shift, how many machines will be required?
(b) It so happens that only two milling machines can be spared for this emergency job, due to other priority jobs in the department. To cope with the emergency situation, plant management has authorized a three-shift operation for six days next week. Can the 1000 replacement parts be completed within these constraints?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Automation Production Systems and Computer Integrated Manufacturing